July 9, 2022 Porte Cochere Progress

July 9, 2022 Porte Cochere Progress

As we await the final approvals regarding our utilities conveyance, some important progress came last week: the ProAudio crew worked on our A/V system and HVAC crews were working above to regulate the flow of cool air.

Views from Tuesday show the completed screen and projector setup and equipment in the sound booth.

County inspectors approved the sprinkler system in the porte cochere, so on Friday, the crew was able to continue building the structure

Ceiling panels for the spaces between the “clouds,” were delivered

Water fountains ready for installation!