Download
Read moreMaking Progress
September 18, 2021 Praise the Lord for the drier days we have had this week! A lot has happened this past week and there are many photos. Read on to
Read moreSeptember 19, 2021
Download
Read morePreparing Tie Beams
September 11, 2021 There has been a lot of activity on the construction site this week! Fill dirt continues to arrive on the scene as is pictured below, and improvements
Read moreSeptember 12, 2021
Download
Read moreSecuring the Walls
September 4, 2021 This past week the construction crew was getting ready to form tie-beam (rebar and concrete) which will go all the way around the circumference of the facility on
Read moreSeptember 5, 2021
Download
Read moreGoing Vertical!
August 28, 2021 The walls are going up… Pastor Eric is standing in his new office! The block masons make quick work of it. The last photo was taken on
Read moreAugust 29, 2021
Download
Read moreVisible Progress
August 21, 2021 Earlier this week, if you had stopped by the construction site you would have been able to see that the cement pad of the foundation had been laid!
Read moreMeet Our New Site Manager
August 14, 2021 Underground electricity and plumbing is complete. Then they sprayed a “termite control” layer before the concrete is poured. Did you know Florida termites eat through concrete? As you
Read moreElectricity is Going in the Ground
August 7, 2021 Electricity is going in! Exciting things are happening at the building site this week. We received the green light to begin the installation of our underground electricity.
Read more







